DEMONSTRATE PROCESS
& DEFINE RESULTS
To earn approval from government officials, Rob Anderson in our USA headquarters flew to Hong Kong to demonstrate the process and define results. While the contractor had air compressors and generators that were compatible with the local electrical systems, they did not have spraying units needed for this project. We retrofitted and shipped high-speed, high-pressure coating equipment and product from the U.S. facility. It required 380 volt, three-phase wiring and a transformer box. Everything was then mounted on a flatbed truck for mobility.