Concrete Floor Grinding:
Diamonds, Grits
and a Flat Slab

Which grinder, which diamond bond and which grit to start with, how far to go before a coating, and how to keep the dust in the vacuum.
Floor prep

Grinding before a coating? Get it quoted as one job.

Tell us what is on the slab now and what you want on it next. We will connect you with a certified ArmorThane applicator who preps and coats the floor under one scope.

  • Floor size and layout
  • Current surface: bare, sealed, painted or coated
  • Joint lips, cracks or spalls
  • Planned coating or finish
Rather talk now? Call (417) 831-5090
Step 1 of 3
CSP 1–3
Profile range a diamond grinder normally leaves
Grinding is ICRI chip 2
2–9
Mohs range concrete floors test across
Scratch pick test
16–40
Starting grit for coating prep and removal
Metal bond diamonds
175 cfm
Minimum vacuum airflow for a 7 in cup wheel
OSHA: 25 cfm per inch

Concrete floor grinding is where most coating jobs are won or lost, long before anybody opens a kit. A grinder with metal-bond diamonds cuts off the weak cement skin, knocks down joint lips and strips thin coatings, and it leaves a flat, open surface a primer can soak into. Pick the wrong diamonds and you will either glaze the floor shiny or burn through a set of segments before lunch.

Quick answer

Concrete floor grinding uses a walk-behind machine fitted with metal-bond diamond segments to remove the top skin of a slab, flatten high spots and take off thin coatings. For coating prep, crews usually start at 16 to 40 grit and stop at an ICRI CSP 2 to 3 profile. Match the bond to the slab: soft bond for hard concrete, hard bond for soft concrete, confirmed with a Mohs scratch test.

Equipment

Concrete floor grinding machines compared

Three kinds of machine do almost all the work. On a garage you might get by with one; on a warehouse you will use all three in a day.

MachineTypical width (in)Best atWatch for
Hand grinder with cup wheel5–7Edges, corners, around posts and drainsGouging; needs a shroud and a vacuum sized for the wheel
Edge grinder7–10Running tight along long wallsLeaves a different scratch than the main machine
Single-disc (rotary) grinder10–17Small rooms, thin coating removal on a budgetSwirl marks; it wants to pull sideways
Planetary grinder16–32Flat, even prep on open floors; polishingNeeds 220 V or 3-phase power and a matched dust collector
Ride-on or remote planetary32+Large warehouses and distribution floorsPower supply, weight on suspended slabs, transport
Typical sizes on the market. A 20 inch planetary is rated as high as 500 sq ft per hour by one manufacturer; real coating-prep speed is lower. Tap a column heading to sort.

Planetary heads are the reason grinding took over thin-coating prep. Several small heads spin one way while the whole deck turns the other, so the scratch pattern crosses itself and comes out even. A single-disc machine cuts in one direction and leaves arcs you can see through a clear coat.

Read the slab first

Mohs scratch test and diamond bond

Diamonds cut. The metal matrix around them, the bond, decides how fast fresh diamonds get exposed. Hard concrete barely wears the bond, so you need a soft bond that sheds and keeps sharp diamonds on the surface. Soft concrete is abrasive and eats a soft bond alive, so it needs a hard one. Guessing wrong costs real money in segments and hours.

  1. Pick three spots

    Test the middle of the floor, near a wall and along a heavy traffic lane. Troweled skins and repaired areas can read very differently.

  2. Scratch from soft to hard

    Drag each Mohs pick across the surface with firm, even pressure, starting at 2 and moving up.

  3. Wipe and look closely

    A real scratch is a groove you can feel with a fingernail. A gray line that wipes off is pick metal, not a scratch.

  4. Record the first pick that cuts

    That number is your hardness reading. Re-test after the first pass, because the surface under a hard troweled skin is often softer.

Mohs 2–3

Soft concrete

Low-strength, dusty or weathered slabs. Use a hard bond, or the segments will wear down fast.

Mohs 3–5

Medium concrete

The most common reading on garage and shop floors. A medium bond does the work.

Mohs 5–7

Hard concrete

Hard aggregate or a heavy power trowel finish. Use a soft bond so diamonds keep exposing.

Mohs 7–9

Very hard concrete

Burnished industrial floors. Extra-soft bond, fewer segments for more head pressure, and patience.

Two warning signsSegments that look shiny or dark and feel smooth are glazed: the bond is too hard and has stopped cutting. Segments that lose height within minutes are too soft for that slab. Either way, stop and change tooling rather than adding weight and hoping.
Selector

Which diamonds should you start with?

Enter your scratch test result and the job. The selector suggests a bond class, a starting grit, the tool style and the profile to stop at. Use it as a starting point for the first test pass, then let the floor tell you.

Tooling match

Concrete grinding tooling selector

Bond class follows the Mohs bands published with Lavina's scratch kit (soft 2–3, medium 3–5, hard 5–7, very hard 7–9) and the inverse rule: harder concrete, softer bond. A hard troweled skin bumps the reading one step for the first pass, which is our field rule, not a published one. Grit starts follow common tooling-maker guidance (16/20 for fast removal, 30/40 as the general start, 60/80 for cleanup). Profile targets follow the ICRI chart: sealers CSP 1, thin films CSP 1–2, high-build systems CSP 2–3.

—
Bond class
—
Starting grit
—
Stop at profile
—
Planned passes

Need a deeper profile than a grinder gives? Our guide to shot blasting concrete covers CSP 3 to 5 prep. Coming off old paint first? See how to remove paint from concrete.

Grit sequence

How far to grind for each finish

Lower grit numbers mean bigger diamonds and deeper scratches. For a coating you want the scratch, so you stop early. For polished concrete you keep refining until the scratch is gone. Mixing those two goals is how floors end up too smooth for the coating that goes on them.

Coatings

Epoxy, polyaspartic, polyurea

One or two passes at 16/20 or 30/40 metal bond, crossing directions. Vacuum, then check the profile against the CSP chips. A floor taken to 80 or 100 grit can be too closed for a thick system, even though it looks great. See our polyaspartic floor coating guide for the system side.

Polished concrete

Grind, hone, polish

Metal bond to open the slab, then transitional or resin pads through progressively finer grits, with a densifier in the sequence. It is a different trade with different targets; our polished concrete vs epoxy page compares the two.

Coating removal

Thin paint and sealers

Aggressive single-segment metal bond at 16/20 opens the film fast. If the coating melts and smears instead of powdering, the segments are loading up; switch to PCD.

Heavy removal

Thick epoxy, mastic, glue

PCD tooling first. It scrapes the film instead of sanding it. Then follow with 30/40 metal bond to clean up and set the profile for the new coating.

On the floor

Dust, edges and flatness

Concrete floor grinding makes fine silica dust faster than any shop vac can handle. OSHA's construction silica standard lists walk-behind floor grinders in Table 1: run them wet, or with a dust collector providing the manufacturer's recommended airflow and a filter of 99% or better efficiency with a filter-cleaning mechanism. Hand grinders need 25 cfm of airflow per inch of wheel.

  • Edges match the field: grind edges with a similar grit so the profile at the wall matches the middle. A smooth edge band is where peeling starts.
  • Lips first: knock down joint lips and high spots before the profile passes, or the coating will show every one.
  • Fill after grinding: grinding opens pinholes, bugholes and cracks. Fill them once the slab is clean; see our spalled concrete repair guide for deeper damage.
  • Vacuum twice: once after grinding and once just before priming. Grinding dust left in the pores becomes a bond breaker.
  • Check moisture: a freshly ground slab is open and will show moisture problems fast. Test before any coating goes down.
Field noteThe most common failure we see on ground floors is a profile that was fine in the middle and polished smooth at the edges, where a crew ran a worn cup wheel to save time. The coating holds in the field and lifts in a neat strip along every wall. Match the edges.

For DIY or small shops, a 20 inch rental planetary will prep a two-car garage in a day. On large or hard slabs, hire it out. Certified applicators who grind and coat with ArmorThane systems, from garage floor coatings to industrial flooring, own the tooling and the dust collectors to do it right.

Ground right, coated right

One crew for the grind and the coating.

A certified ArmorThane applicator can quote the floor grinding and the coating system together, so the profile matches what the product needs.

Contractors: become an ArmorThane applicator

FAQ

Concrete grinding questions

What grit should I use for concrete floor grinding before epoxy?

Most crews prep for epoxy with 30/40 grit metal-bond diamonds, dropping to 16/20 if there is a sealer, paint or uneven surface to cut through. Stop there. Going to 80 grit or finer can leave the floor too smooth for a high-build coating.

Is grinding better than acid etching?

Yes, for any coating that has to last. Grinding removes the weak top layer and leaves a measurable, even profile. Acid etching reaches CSP 1 at best, leaves salts that have to be neutralized and rinsed, and soaks the slab right before it needs to be dry.

How do I know which diamond bond to use?

Do a Mohs scratch test. Readings of about 2 to 3 call for a hard bond, 3 to 5 for medium and 5 and up for a soft bond. If segments glaze, go softer; if they wear down in minutes, go harder.

Can you grind concrete without making dust?

Not without control. Grind wet, or connect the shroud to a dust collector with the airflow the grinder maker recommends and a filter rated 99% or better. That setup keeps most dust in the bag, but silica exposure still needs to be managed under OSHA rules.

Can I grind my own garage floor?

Many owners do, with a rental planetary grinder, an edge grinder and a proper dust collector. Expect a full day on a two-car garage. The hard part is reading the slab and matching tooling, which is where a professional crew saves time.

Does grinding level a concrete floor?

It flattens joint lips and small high spots, usually a fraction of an inch. It will not fix a slab that is out of level by inches or badly sloped; that takes a self-leveling underlayment or a concrete overlay.

AT
Written by the ArmorThane technical team. We have manufactured polyurea, polyurethane and polyaspartic coatings and plural component spray equipment in Springfield, Missouri since 1989. Grit and bond guidance here is typical; follow your tooling maker's recommendations and the coating data sheet for the profile it requires.

Sources

  1. OSHA, 29 CFR 1926.1153 Respirable Crystalline Silica, Table 1. osha.gov/laws-regs/regulations/standardnumber/1926/1926.1153
  2. Lavina, Mohs hardness tool guide (concrete hardness bands and bonds). s3.amazonaws.com/Niagara-Library/.../mohs-tool-guide-pds.pdf
  3. Bartell Global, What makes concrete hard, medium or soft. blog.bartellglobal.com/what-makes-concrete-hard-medium-or-soft
  4. Grand Diamond Tools, Diamond grinding segments for concrete: bond, grit and style. granddiamondtools.ca/blogs/.../choose-diamond-grinding-segments-for-concrete
  5. TCC Materials, Concrete Surface Preparation Profiles (after ICRI 310.2R). tccmaterials.com/ConcreteSurfaceProfiles.pdf

Flat, open and ready to coat.

A certified ArmorThane applicator grinds to the profile your coating needs and sprays the system the same project. Contractors can add floor coatings with our equipment and training, with no franchise fee and no royalties.

United States 417-831-5090 · Canada 780-444-6200

CONTACT US

REQUEST A QUOTE OR

BECOME AN APPLICATOR

ArmorThane has built a strong reputation over the past 30 years for producing high-quality, durable protective coatings.

group 115 660555abebfe4
Phone Number

Tel: 417.831.5090

group 115 1 660556c21395c
Email Us

moreinfo@armorthane.com

Step 1 of 3

We want to help you find the best ArmorThane applicator for your protective coating project. Please either fill out the request form below or call us toll free at 417-831-5090, any time Monday-Friday, 8:00 a.m. to 5:00 p.m. Central Standard Time.

RV Find An Applicator

Protective Coating Applications

Products

Applicator Opportunities

Knowledge Center

Galleries